2024

2024-06-10 thru 2024-06-15 Sections of Tanglewood Drive were removed and replaced with asphalt.

2023

A damaged area of the roadway two months prior to repair. (The image location needs to be verified.)

The images below are of the same area as above and were taken shortly after three bags of Gevenko ChipFill were applied to the roadway on 3 June 2023. (The name and amount of the material needs to be verified)

Repair crew: cb and hp